ProjectMarch 02, 2026
Shipboard Crane Load Test & Inspection – Fujairah Anchorage
- Fujairah Anchorage, UAE
Precision. Procedure. Performance.
As part of routine marine lifting assurance, comprehensive load testing and detailed inspection were successfully completed onboard at Fujairah Anchorage.
Here’s a snapshot of the testing carried out
- Midship Crane
SWL: 2.04 Tons
Test Load Applied: 2.55 Tons
- Provision Crane
SWL: 0.97 Ton
Test Load Applied: 1.21 Tons
- Engine Room Overhead Crane
SWL: 1 Ton
Test Load Applied: 1.25 Tons (Static Pull Test)
Before Load Application
- Detailed visual inspection
- Structural assessment
- Brake & safety device checks
- Functional operational testing
Testing Focus
- Structural integrity
- Braking performance
- Operational reliability
All inspection and testing procedures were carried out in accordance with Lifting Equipment Engineers Association (LEEA) standards.
Result
All cranes were found satisfactory and are safe for continued operation within their respective SWL limits.
Because at sea, lifting safety isn’t optional — it’s operational discipline.