Crane Load Test & Annual Inspection – Khalid Port, Sharjah
Location: Sharjah Khalid Port, United Arab Emirates
Routine crane load testing and annual inspections were successfully completed to verify operational safety and compliance with international lifting equipment standards.
LOAD TESTING COMPLETED
- Pump Cranes (2 Nos.)
SWL: 30 kN
Test Load Applied: 37.5 kN
- Main Deck Crane
SWL: 100 kN
Test Load Applied: 125 kN
ANNUAL INSPECTION CONDUCTED
- Engine Room Crane
- Deck Crane – Port Side
- Provision Crane – Starboard Side
- Lifting Support Equipment
All above cranes are rated at
SWL: 30 kN
Test Load: 37.5 kN
PRE-TEST INSPECTION
Before conducting the load testing, a comprehensive visual inspection was performed covering
- Crane Structural Components
- Wire Ropes Condition
- Hooks and Lifting Accessories
- Mechanical & Operational Integrity
TEST RESULTS
- All cranes operated within Safe Working Load (SWL) limits
- Load tests completed successfully
- Equipment verified for operational safety
- Standard certification issued
All inspection and load testing procedures were conducted in accordance with LEEA (Lifting Equipment Engineers Association) standards.
Status: Inspection Completed
Certification: Issued
Compliance: LEEA Standards